Skip to main content

Cookies on BBB.org

We use cookies to give users the best content and online experience. By clicking “Accept All Cookies”, you agree to allow us to use all cookies. Visit our Privacy Policy to learn more.

Cookie Preferences

Many websites use cookies or similar tools to store information on your browser or device. We use cookies on BBB websites to remember your preferences, improve website performance and enhance user experience, and to recommend content we believe will be most relevant to you. Most cookies collect anonymous information such as how users arrive at and use the website. Some cookies are necessary to allow the website to function properly, but you may choose to not allow other types of cookies below.

Necessary Cookies

What are necessary cookies?
These cookies are necessary for the site to function and cannot be switched off in our systems. They are usually only set in response to actions made by you that amount to a request for services, such as setting your privacy preferences, logging in or filling in forms. You can set your browser to block or alert you about these cookies, but some parts of the site will not work. These cookies do not store any personally identifiable information.

Necessary cookies must always be enabled.

Functional Cookies

What are functional cookies?
These cookies enable the site to provide enhanced functionality and personalization. They may be set by us or by third party providers whose services we have added to our pages. If you do not allow these cookies, some or all of these services may not function properly.

Performance Cookies

What are performance cookies?
These cookies allow us to count visits and traffic sources so we can measure and improve the performance of our site. They help us to know which pages are the most and least popular and see how visitors move around the site. All information these cookies collect is aggregated and therefore anonymous. If you do not allow these cookies we will not know when you have visited our site, and will not be able to monitor its performance.

Marketing Cookies

What are marketing cookies?
These cookies may be set through our site by our advertising partners. They may be used by those companies to build a profile of your interests and show you relevant content on other sites. They do not store personal information directly, but are based on uniquely identifying your browser or device. If you do not allow these cookies, you will experience less targeted advertising.

Find a Location

Father & Sons Home Improvement II, Inc. has locations, listed below.

*This company may be headquartered in or have additional locations in another country. Please click on the country abbreviation in the search box below to change to a different country location.

    Country
    Please enter a valid location.

    ComplaintsforFather & Sons Home Improvement II, Inc.

    General Contractor
    View Business profile
    View Business profileBBB accredited business

    Need to file a complaint?

    BBB is here to help. We'll guide you through the process.

    File a Complaint

    Complaint Details

    Note that complaint text that is displayed might not represent all complaints filed with BBB. See details.

    Filter by

    Showing all complaints

    Filter by

    Complaint Status
    Complaint Type
    • Complaint Type:
      Service or Repair Issues
      Status:
      Answered
      My husband and i did not place a complaint as we were advised that someone would come out to correctly install the stack pipe that was not installed at the time of construction completion. Foul sewer smells started filling up our basement as the weather became cold, my husband contacted ****************************** they sent someone out. He placed a pipe through the basement wall illegally as a solution which is not a solution at all. Foul smells are is a problem in the basement. $2,000.00 initial down payment. Initial contract agreement, $67,900.00. $20,000.00 was added because the demolition person took down a wall he was not to take down. I argued the issue but to no avail i was still charged the fee. Asked how $87,900.00 turned into $91,658.96 with ******* Financial I never received an explanation.Currently with ************************. $72,251.57. My husband and I have contacted plumbing companies which are reluctant to take our business with the exception of Four Seasons. There price to correct or install a stack pipe after construction is well above what we can afford presently.

      Business response

      01/09/2024

      Hello *********************,

      We apologize for the delay, and we appreciate your patience. We are going to take care of the kitchen vent. *********** will be contacting you soon. Regarding your loan, you need to contact your lender. Attached is a copy of your contract and the change order.

      August 2016                  - Signed a contract for $67,900.00. Copy attached.
      September 2017           - signed a change order for $18,300.00. Copy attached.
      December 2017            - Signed a change order for $1,400.00 new electrical panel
      February 2018              - Extra for tile over the allowance of $334.03
      All permit fees              - $3,450.00

      The total for the above $91,384.03

      Payments received from ********************** $87,650.00
      Payment received from property owner $3,734.03

      We hope the above clarifies all your concerns.

      Customer response

      01/09/2024

       
      Complaint: 21108898

      I am rejecting this response because:  Father & Son's sold my husband a contract agreement, purposely over demoed the upper level of our home, then added a change order to fix with the charge of $18,300.00. With our upper level of our house exposed to the elements we pleaded with Fathers & Son's the this additional cost was unfair.  The weather had changed, we were getting rain and snow mixed onto the open demoed area of our home with water damaging the first floor ceilings. With that being said and no other recourse we signed the change other.  As far as the cement siding, why would you add that to a contract knowing that the ******* or ******** code is to use cement siding and not vinyl siding. Bait and switch tactic because there were multiple home Father & Son's were working on simultaneously in my zip code area.  My husband and I are contesting the charges for the December ************************ the February 2018 extra tile allowance of $334.03.  We are still requesting that Father & Son's complete the stack pipe that they neglected to install during construction.  If there was a good faith effort to correct the uninstalled stack pipe the plumber who came out to correct the missing stack pipe would not have illegally installed a pipe out the side of the wall.  The fact that Father & Son's sold our mortgage to another lender m does not change the fact that the original charge of $18,300.00 should be refunded by to ****** and ******************************  Our address is still the same.  Lastly, we look forward to the visit from the 3 plumber  or Father & Son's representative. Just want a stack pipe installed correctly with a start date of installation, the name of the representative that will complete the work and the time frame the work will be completed 

      Sincerely,

      ****** And *****************************

      Business response

      01/10/2024

      Dear Mr. ***** *********************,

      We appreciate you contacting us; however, we cannot refund you. The work at your home was completed in March 2018. If you were not happy with us, why did you let us proceed with the work and let us complete it?
      ******************** signed both change orders for the additional work and agreed to the additional cost, and all the work was completed.

      The original contract was for one bedroom and bathroom and vinyl siding installation. The change order was to remodel your front attic and install cement siding. The *************** requested cement siding due to the special conditions of your home. Your lender paid the extra cost. Attached is a copy of the contract and change order. 

      The change order for the electric was to upgrade your existing panel and the additional cost of $334.03 was the amount over the allowance for your ceramic tile. The allowance was $2.00 per sq. ft.
      We explained these two charges to you, and you issued a check to us for the additional cost. 

      Your job has been completed for almost six years. We are amazed to receive this complaint from you after the work has been completed and you agreed to all the additional work performed on your home. 

      Regarding your loan, please contact your lender; you never had a loan with us.  

      Kindly contact our project manager, ******, at ************ to schedule an appointment with the plumber. ****** spoke with your husband yesterday, and he informed ****** that he would contact us to schedule an appointment. After the plumber inspects the property, we can provide you with a schedule to extend the kitchen vent pipe.

      Thank you for contacting us. We hope we have answered all your concerns; we will take care of your kitchen vent as soon as possible. 

      Customer response

      01/11/2024

       
      Complaint: 21108898

      I am rejecting this response because: You can refund the $18,300.00, the change order for additional work was after your worker completely demolished our upper level of our home without written consent from neither of us. The original contract as stated by you was only for one bedroom and bathroom and vinyl siding installation not to remodel our front attic, we specially informed your project manager prior to demolition started.  The fact the you hired personnel who clearly did not follow instructions should not be me nor my husbands financial burden.  The order was signed under duress as my husband and I had no other recourse but to continue with your company to complete the work and to avoid a property lien.  You also knew from experience that no other company would take on the job after permits were pulled and contract's were signed. 

      To answer your question if we were not happy with Father & ***'s why did we let your company proceed with the work until completion. Well let me answer that for you. First of all our entire upper level was torn completely off exposed to inclement weather, cold and wet rain mixed with snow. Your construction crew nor your project manager ordered did not have the wherewithal to cover the exposed are with a tarp or some kind of covering which lead to ceiling damage on the lower area of our home.  

      Also, over the course of six years my husband has been in contact with the original project manager, the second project manager after your first project manager was fired and for the last couple of years your office manager ***********  Over the six years my husband and i have been promised corrective action and are stilling waiting for that to occur. 

      The vinyl tile situation is on you or your company as you knew what the *************** required for my type of home as you began to pull permit's prior to construction in 2016, that should be apart of planning on you part and should not be charged to your customers due to your lack of planning,.

      The refund should come from Father's & Son's and not the lender ******* Financial at the time because the charge was originated with Father's & ***'s not the lender. Also ******* Financial did not take care of monies as you stated, plus we were advised by the owner of Father's & Son's or the sales man that came to our home who also signed the original contract that Father' & Son's owned ******* Financial so not to worry about getting the loan. 

      I am asking the you pull a permit from the *************** for the work that will be completed by ****** or whomever you designate to complete the work. We want a guarantee that this time the work is done correctly as it was not correctly done at the completion of construction.  Lastly, have ****** or whomever is designated to remove the illegally installed vent through our basement wall and properly seal the hole in the wall 


      Sincerely,

      ****** And *****************************

      Business response

      01/11/2024

      Hello Mr. ***** *********************,

      We informed you of all the additional work that had to be performed at your home, and we provided you with a written change order that you signed and agreed to the work and additional cost. Attached is a copy of the front and back of the contract and change orders.

      Our work was completed in 2018, and this is the 1st time you have contacted us requesting a refund for a project that was completed almost six years ago. 

      Please review the following paragraphs:
      6.5          Owner warrants and agrees to assume full responsibility that the improvements called for hereunder conform to local building codes and local zoning ordinances, are constructed within the boundaries of Owners property, and are otherwise permissible under local codes and ordinances.
      6.5.1.      Owner authorizes all necessary changes to the Drawings and Specifications in this Contract to enable the Work to be completed in accordance with local building codes and zoning ordinances, and agrees to pay for such changes.
      9.0. CONTRACT MIDFICATIONS AND CHANGED ORDERS.
      9.1.         During the pendency of this Contract, the parties may agree to modify this Contract by changing the work to be performed or the materials to be provided. This may or may not include a change in the Contract Sum. All such modifications shall be by written Change Order signed by both Parties except as noted below.
      9.1.1.      If a modification is required on an emergency basis, the parties may agree to the same orally, in which case the Contractor shall be authorized to proceed, and the Owner agrees that the additional amount due the Contractor as a result of such modification shall be an additional sum due hereunder. 
      9.1.2.      Any and all changes made necessary by building code, ordinances or statutes pertaining to the Premises shall be charged to the Owner and added to the amount due the Contractor. 

      We will extend your existing kitchen vent pipe and any patchwork needed after the kitchen vent is extended. We will contact you to schedule the work as soon as we obtain a building permit from the *************** to extend the kitchen vent pipe. 

       

      Customer response

      01/11/2024

       
      Complaint: 21108898

      I am rejecting this response because: This is the first time ever seeing The General Conditions of Contract that was never presented to my husband or myself as you know this to be a fact.  All events stated actually happened as we stated which you are very aware of.

      Unscrupulous business practices of having a worker tearing down the front attic that was never agreed upon to be torn down and presenting it as  a change order to us to cover your mistake with a charge of $18,300.00 is just plain unjust.

      And please do not try to act as if my husband has never contacted your company until now. As previously stated my husband did his due diligence over the period of 6 year's, Father's & Son's neglected to do their's. We filed this complaint with the Better Business Bureau because we could not get your company to complete the work from the original construction date. 

      With that being said, we do look forward to the City Permit for the work that should have been completed before the end of construction work completed. Please have someone to contact us with an actual plan of action containing a start and time of completion date. 

      Sincerely,

      ****** And *****************************

      Business response

      01/11/2024

      We provided you with a copy of the general conditions of the Contract. This page is on the back of your original Contract.

      A modification had to be made, as stated in our Contract.
      9.0.      CONTRACT MODIFICATIONS AND CHANGED ORDERS.
      9.1.      During the pendency of this Contract, the parties may agree to modify this Contract by changing the work to be performed or the materials to be provided. This may or may not include a change in the Contract Sum. All such modifications shall be by written Change Order signed by both Parties except as noted below.
      9.1.1.   If a modification is required on an emergency basis, the parties may agree to the same orally, in which case the Contractor shall be authorized to proceed, and the Owner agrees that the additional amount due the Contractor as a result of such modification shall be an additional sum due hereunder.
      9.1.2.   Any and all changes made necessary by building code, ordinances or statutes pertaining to the Premises shall be charged to the Owner and added to the amount due the Contractor.

      We provided you with a change order, and you agree to the additional work and the cost to perform the work.
      ******************** contacted our office to inform us of the kitchen vent pipe.
      We have never received a complaint from you or ******************* before regarding the cost of the project. It has been almost six years, and we do approximately 25 additions a year. We cannot recall precisely every detail of the project, but our notes show that ****, your superintend at the time, took to you the change order for review and approval; if you were not satisfied with the cost of the work, you should have negotiated the price before the work was completed. After all these years, you cannot ask us to refund you the money; the work was done, and the additional materials were purchased. We cannot refund you for the work that was performed. 

      We have submitted a building permit request to the *************** this today; we are waiting for the plumber to submit additional information to the city. As soon as the permit is ready, we will contact you to schedule the work and discuss the plan with you and the completion date.  

      Customer response

      01/11/2024

       
      Complaint: 21108898

      I am rejecting this response because:  We agreed to the additional work and the cost to perform the work after I was told by *** that there was no other recourse even if though the complete demolition was a mistake, that in itself is an actual complaint. The fact that *** acknowledged the complaint and advised that the charge would stay whether I contested it or not should also be taken into consideration.

      As a customer we were being faced with no upper floor that is exposed to inclement weather rain and snow mixed, no tarp or plastic cover damaging the ceiling on the main floor of our house. Again you knew that we could not get other company to come in and continue the work that began with your company. Permits, blue prints, zoning, etc. took your company a year to clear before work could began.  Again being placed in a situation like this and signing your Change Order occurred was under duress. 

      The fact that my husband contacted your office to inform you to inform you of the kitchen vent pipe is a complaint. So how could you state that you never received a complaint. 

       Over the course of almost six years, you should have sent someone out to correct or install the vent pipe instead of denying that we never reached out to you, which we did on more than one occasion. 

      Not recalling precisely every detail of a project because you do approximately 25 additions a year is lack of documentation of events on your part, and is not a defense. As i remember the details along with your replacement superintendent, ***** replacement, and **********; your office manager.  The fact that that information was not shared with you is an internal problem and should not be used as a defense. 

      The notes that you state **** your superintendent were most likely fabricated as he was always missing in action or smell of alcohol when he finally showed up on site.  

      You forget that i did stated that i was not satisfied with the cost of the work, and I did speak to *** to negotiate the price before the work was completed.  Again when you know that your customer does not have the choice of going with some other company because your company demolished the upper floor of their home, the only recourse is to sign a Change Order under protest which is considered duress. 

      After all these years,  I can you ask us to refund you the money or a portion of if work has been completed, additional materials purchased in all. 

      You can also refund the actual amount or a portion of it as the complete demolition was not agreed upon, it was a decision made by and unsupervised worker, your worker, and not me or my husband.  

      Thank you for submitting a building permit request to the *************** today.  We will be waiting for assignment of the plumber to submit additional information to the city.

      Thank you for reaching out to us as soon as the permit is ready, and contacting us to schedule the work and discuss the plan with us along with the completion date.  

      Sincerely,

      ****** And *****************************

      Business response

      01/12/2024

      Good morning, *********************,

      This morning, we submitted the information the City requested; we will let you know as soon as the permit is ready.

      The additional work performed at your home was to remodel your attic space and install the cement siding. We would have never left your home exposed to the elements. Every time we build an addition, we cover it with a tarp; if any damage is done to your home, we fix it. Attached are numerous customer satisfaction forms you signed throughout the job; for each customer satisfaction, you have the opportunity to address any complaints; you only had one complaint on 12/8/17; we took care of the issue, and the rest of the customer satisfaction, you had no complaints or dissatisfaction with our work.

      As we mentioned, the only complaint we received from you is about the kitchen vent. ******************** called us in October 2022 to inform us that an HVAC company that worked at your home told him that the kitchen vent had to be extended through the roof. We guaranteed him that we would take care of it; unfortunately, we were short of men, and the plumber at that time was unavailable; now, we have a different plumber ready to start the work. We appreciate your patience. 

      Regarding the change order, you agreed and signed all the documents. We are not fabricating any documents, as you claim in your response. All the documents were reviewed, approved, and signed by you. 

      As stated in our contract: 

      Paragraph 9.1.1 of the back of the contract: 
      9.1.1.      If a modification is required on an emergency basis, the parties may agree to the same orally, in which case the Contractor shall be authorized to proceed, and the Owner agrees that the additional amount due the Contractor as a result of such modification shall be an additional sum due hereunder. 

      We will contact you as soon as we have the building permit. 

      Customer response

      01/12/2024

       
      Complaint: 21108898

      I am rejecting this response because: Thank you for starting the process of installing the vent pipe by starting with the permit.

      My husband and I are not contesting the work completed because we were and still is pleased with the work that was completed.  ***** being my favorite contractor because he really was exceptional.

      The issue or the complaint is nor was it ever about not being satisfied with all of the work performed, it has been only been about the forced Change order, it cost that was not absorbed by Father's & Son's instead it was $18,300.00 which is a lot of money charged to us. 

      The complaint was also about the missing vent pipe that was missed by your incompetent worker or contractor who was  responsible it's install.  

      The customer satisfaction report documents do not negate (nullify) the fact that the signing of the Change Order was signed under duress because our roof was left completely exposed to inclement weather, you knew that we had no other options but to continue with the build.

      So please don't insult my or my husbands intelligence by saying that your contractor' covered our roof, which they did not. The ceiling damage was taken care of by my husband, thank you for your lack of help. 

      Please refer back to my previous written statements or complaint concerning why we are seeking reimbursement of monies that was erroneously charged for a big, huge mistake by your unsupervised employee or contractor. 

      Sincerely,

      ****** And *****************************

      Business response

      01/15/2024

      Hello, Mr. ***** *********************,
      The *************** has issued the building permit for us to extend the kitchen vent pipe. Please let us know what day works better for you so we can schedule the work.
      The plumber first has to open the wall to extend the kitchen vent pipe, and then we need to contact the City to request an inspection;depending on how busy the City is, this can take more than a week. After the City has inspected the work and approved the job, we will schedule our ********* to stop by your home and patch where the plumber made openings. The ****** superintendent will give you more information.
      Regarding the refund, as we explained to you, there is no refund. We did nothing wrong; a modification had to be made; we provided you with a change order, you agreed to it, and we did the work.
      We have attached a copy of the preliminary drawings you reviewed and approved after signing the contract. You agreed to the following:

      Owner agrees that contractor shall not be responsible for minor deviations from the drawings and /or contract. Deviations may also be necessiated by Governmental approvals. There shall be no credit or decrease in contract price for such deviations.

      Please contact our office or ****** directly to schedule an appointment.

      Thank you! 

       

      Customer response

      01/17/2024

       
      Complaint: 21108898

      I am rejecting this response because: The original draft or floor plan confirm's signed 9/10/16 that the front attic was not included and not expected. I also confirm's that the front attic demolition *********************** not by your unsupervised worker forced a Change Order to occur. And as previously stated leaves homeowners or customers no other recourse but to sign it regardless of your verbiage within the second floor plan's. 

      The clever statement included on the draft, Owner agrees that contractor shall not be responsible for minor deviations from the drawings and or contract. Speaks to my complaint that the front attic area demolition felt intentional on your part as it has most likely occurred with more than one customer or home owner, why else would it be added. 

      There shall be no credit or degrease in contract price for such deviations, it should state that mistakes on the behalf of our workers will not be charged to our customer or homeowners. Your mistake that cost us $18,300.00 

      Your company, your rules. Looking forward to ****** correctly removing the illegally installed vent pipe through our basement wall, correctly installing the new vent pipe moving forward. 


      Sincerely,

      ****** And *****************************

    • Complaint Type:
      Order Issues
      Status:
      Answered
      Contract issue with Father and Son Home Improvement II.Here is what has happened in sequential order:1. Back in October 2021: Signed Contract with Father and Son Home Improvement II to add a garage, add a 2nd floor, replace the Roof, Add a Bay Window to livingroom. I gave thema $50,000 check as deposit.2. I was told that the permits would take from 3 to 5 months and then the house project would start right away.3. Father and Son Team including their assigned Architect(*****) have been having so many delays/issues getting these required city permits for my house project.4. After the 4th month(March 2022) from when I signed the contract, I've called father and son team on a weekly basis to get status and all I get is the same status... that they are waiting for the city to approve the needed permits.5. Five months later I had a phone conversation with ***(Owner) and he mentioned that it was my fault because I would not agree to some architural changes in the contract and the city would not approve it as originally designed... which I did not like(reducing the size of the 2nd floor). We finally agree that instead of reducing the 2nd floor it would be exted on the back of the house(same dimentions). I didn't like the new design but just get the city permits approved asap.... which turned out to be a lie because they are sitll having issues.6. Six months later(around 09/2022), I was still getting the same status from father and son... so I decided to go to ******* ******************* in person and they told me that the Application was cancelled due to "Father and Son and or the architect(*****)" have NOT replied back in more than 120Days. So I called father and son right away and they have a private meeting with their Architect.7. Architect re-applied for the same city permits... and I believe everything started from the beginning, again. this was back in October ******. As of August 2023, I'm still waiting for Father and Son to get the city permits.

      Business response

      08/09/2023

      We understand ****************** is very frustrated and eager for us to start his project. We are also frustrated and eager to begin his work. We appreciate his patience and thank him for choosing our company to work in his home. Unfortunately, we cannot start the construction project without a building permit. The Architect, *****************************, has been working with the ***************, and because of the unique conditions of his house, it has been taking longer than we expected to obtain the building permit.

      The architect informed us that the initial permit application expired as the design changes could not be agreed upon several revisions were made, including adding scope of work.

      During the second permit application, the building department wanted the new permit drawings to include the owner's *******************, which the owner did not inform us of.

      Currently, the architect is working with the ****************** Administrative Adjustment application was submitted to the ***************** due to the special conditions of the property. We have submitted notices to the adjacent neighbors and ********, pictures of every house on the block from both sides, a block site plan reflecting the side setback and front setback of each property, and recently, the ***************** requested a block site plan reflecting the rear setbacks of every property on the block the architect is still working on this. We will submit the drawings to the ***************** for review as soon as he completes the drawings.

      Again, we want to thank ****************** for his patience,and we hope to obtain his building permit soon, so we can start his remodeling project. Attached is a copy of the Building Permit Application Status from the ***************. 

      Customer response

      08/15/2023

       
      Complaint: 20438929

      I am rejecting this response because: Father and Son has been using this excuse since about 1 1/2.  It should be unacceptable to take 2 years just to get the city permits... if Father and Son can NOT comply with his contract agreement, they should just say it and so we can cancel this contract and I can find someone else to do the work.  FYI: I am losing about $2000 / Month due having to pay bills for 2 houses until they complete the work on the house so I can move in it.  The ******* ******************* keeps telling that they waiting for Architect to provide documents for city permits... currently, the task is with the architect since 7/21 with corrections to complete waiting for Architect.

      We need an ETA when Father and Son will be done with this project of house renovations so I can plan when where to move my family to.

      Waiting almost 2 years is too long and Father and Son needs to be more responsible and at least provide an ETA when all work will be completed... it's been almost 2 years already and every month that passes by I'm losing about $2,000 paying bill for 2 houses... FYI: Currently that house at **** it's empty until Father and Son completes the work.

      Please help me resolve this problem, I'm really desperate to find a resolution for this problem with Father and Son.



      Sincerely,

      ***********************

      Business response

      08/18/2023

      We wish we could do more, but at this moment, the Architect is working with the ****************** We hope to obtain his building permit soon. We are eager to start his contraction project. Unfortunately, at this time, we can't give ****************** a starting date without a building permit. We will provide ****************** with a starting and completion date once the building permit is approved.

      Attached is a copy of our contract, the front and back. Our contract states the following: 

      Contractor assumes no responsibility for any permit delays.

      The Contractor is not responsible for any delays in obtaining the building permit, which are not directly attributable to acts or omissions by the Contractor.

      We truly value ********************** patience, and as soon as we have his building permit, we will contact him.

      Thank you 


      Customer response

      08/25/2023

       
      Complaint: 20438929

      I am rejecting this response because: Father and Son  and their architect need to provide an estimated time when this project will start the actual work.... Waiting almost 2 years, just for work permits, it's unacceptable.



      Sincerely,

      ***********************

    • Complaint Type:
      Service or Repair Issues
      Status:
      Answered
      On June 16, 2022, I signed a contract with ***************************** Home Improvement to complete work on my garage and home. The work was not started until 11/25/22 and was not performed according to the contract. I notified all involved parties (verbally and in writing) at the start of the project on 11/25/22 (including ***************************** Home improvement and the 3rd party contractor) that the work was not performed according to the contract. I also notified the 3rd party contractor and ***************************** Home Improvement again on multiple occasions and requested resolution from Father and Sons Home improvement however they ignored my requests. As of today, ***************************** Home improvement has not and will not provide a resolution. I requested to speak with the owner of the company multiple times for resolution and have also been denied. I recently requested to speak with the owner of ***************************** Home improvement on 1/28/23 and was told that the owner WILL NOT follow up with my request for resolution and was additionally threatened and antagonized by ***************************** Home improvement and its 3rd party contractor. The 3rd party contractor has acknowledged he has not performed the work according to the contract and even with ***************************** Home improvement knowledge of the failure to comply with the full contract, they refuse to resolve the matter in an honest and fair manner. The following items were clearly listed in the contract and was not completed: 1. Re-frame opening for windows 2. Re-frame opening for service door 3. Remove OSB on walls and install it correctly. The company is aware that the tasks were not done and refuse to take accountability or resolve the matter. On 1/28/23, ***************************** Home improvement and its 3rd party contractor confirmed that the framework for the ************* and OSB around the garage was accurately installed prior to hiring ***************************** Home improvement however this contradicts my signed contract! This company is nothing but a scam!!

      Business response

      01/31/2023

      ************** signed a contract with ** on June 16, 2022. Attached is a copy of the Contract. The ******************* approved the building permit on July 21, 2022. Attached is a copy. The building permit was to reframe for garage service door & window soffits. 

      ************** is breaching the Contract by not making her payments. Per our Contract, the payment schedule is as follow:

      20%Down of Payment $1,300.00 PAID
      Permit fees $179.00 Past due
      40% when work starts$2,600.00 Past due 
      30% when half done $1,950.00 Past due
      Balance Upon Completion$650.00 Past due

      The building permit was mailed to ************** on August 3, 2022, with a letter requesting her to remit payment for the building permit. Copy attached. 

      The ******************* inspected and approved our work. Attached is a copy of the inspection report. 

      ************** signed a customer satisfaction when the work was completed. Copy attached. 

      Customer response

      02/01/2023

       Complaint: 18954694

      I am rejecting this response because:

      The building permit and passing of an inspection has nothing to do with this complaint!! The complaint is that you breached the contract by not completing all the work as clearly stated in the contract. Additionally, I've requested the payment be recalculated on multiple occasions both written and verbally for you to adjust the price for the work that you did not perform according to the contract and you have repeatedly ignored the request. Your agent and a witness was present at my home when your 3rd party contractor admitted on 1/28/23 that he did not complete several tasks in the contract. You breached the contract and fail to take responsibility in an honest manner! Instead, you've attempted to go around the topic of this complaint and have once again dismissed your failure to adhere to your contract. 

      Please note the customer satisfaction document attached by Father & Sons Home Improvement is the 2nd customer satisfaction form and has been illegally falsified and altered without my knowledge. 


      Sincerely,

      *************************

      Business response

      02/03/2023

      We want to close this account. We have invested a lot of time and money and have done nothing wrong. ****************** allegations that she did not sign the forms are false. 

      But again, we want to close this account and get paid for the work we performed, and we are willing to give her a $250.00 credit. 

      Contract price $6,500.00
      Permit fees$179.00
      payment received-$1,300.00
      Credit-$250.00 (pending owners approval)

      Balance due$5,129.00

       

      Thank you 

       


      Customer response

      02/07/2023

       
      Complaint: 18954694

      I am rejecting this response because:

       

      A $250 credit is not a fair or reasonable compensation to address the several tasks that you did not complete as clearly stated in the contract. 

       

      Additionally, the original customer satisfaction form was altered after I signed it and provided it to the contractor.  It is clearly evident as it's filled out in a different colored ink and the hand writing is vastly different. It is illegal and fraudulent to alter a document after it has been signed!! 

       

      Take accountability and operate your business in an honest manner! You did not complete several tasks in the contract,  you have illegally altered the document uploaded and even with the proof you still won't take accountability! 

       

      I will not accept a $250 credit, my request is for a full refund!

       


      Sincerely,

      *************************

      Business response

      02/10/2023

      *************** finally answered our phone calls today. We have been trying to contact her to resolve this issue. We are willing and able to correct the items she is not satisfied with at no additional cost to her.However, this morning, she informed us that she did not need us to go back and correct the work that we performed and that our work was inspected and approved by the *******************. Therefore, we do not know what else we can do to resolve this issue. ************** is being unreasonable by requesting a full refund.

      We are trying to work with **************, and if she is not satisfied with our work, we are more than willing to go back and correct it.

      Per our contract Paragraph

      11.2. Owner Dissatisfaction. In the event Owner is in any matter dissatisfied with any aspect of the Contractor's performance hereunder, Owner shall so notify Contractor, in writing by registered mail, of such dissatisfaction within seven business days after the Owner knew, or should have known of any such dissatisfaction.
      11.2.1 Contractor shall have seven business days from the date of its receipt of such notification in which to initiate efforts to resolve Owners concerns, whether by remedying the alleged defective work, providing a credit against the contract price, or otherwise.

      Regarding the customer satisfaction report, we did not change the document after she signed it.

      Customer response

      02/13/2023

       
      Complaint: 18954694

      I am rejecting this response because:

       

      You have not tried to resolve this matter in a fair manner! Your offers were unreasonable and I made that very clear to the owner *** on 2/10/23. 

       

      My request is for a $3000 credit to compensate for the tasks that you did not complete in the contract. 

       

      Again, the customer satisfaction document was altered after I signed it. The comments in black ink is not my writing and not my words! It was clearly altered after i gave it back to the contractor. I've uploaded the original document given to the contractor which I also maintained in my records! 

       

      Sincerely,

      *************************

      Business response

      02/14/2023

      Attached is our response to ************** complaint.

       

      Thank you 

      ***************************

      Father and Sons Home Improvement II, Inc. 

      ***********

      *********, ** 60546

      ************

      Customer response

      02/18/2023

       
      Complaint: 18954694

      I am rejecting this response because:

      The ******************* inspector and 3rd party inspector T.P.I along with the ******************* Building Dpt Commissioner assessed my garage on 2/17/23 and there were many concerns noted and ultimately it failed the inspection. As I stated in my email communication to Father and Sons on February 13, 2023, the ******************* stated the failed 1/17/23 required a re- inspection. At no point did ****** ever communicate that to me instead he took a photo of a 1/20/23 inspection report that stated pass (siding only). 

       

      Furthermore,  I've been stating over and over since November 25, 2022 that the *** needed to be removed and re-installed correctly and the framing for the door and window needed to be re-framed correctly as it is listed in my contract and was also discussed prior to me hiring Father and Son's. Your contractor and ****** came to my home on 1/28/2023 and confirmed tasks were not done in the contract and stated it didnt need to be done because it was already done correctly before your company started any work.  Your company ignored my requests to resolve this matter months ago and ultimately lied and lead me to believe the inspection was passed when in actuality it did not. 

       

      I am requesting an in person meeting with Father and Son's Home Improvement, the contractor,  the ******************* Building dpt Commissioner,  and the inspectors to go over the 2/17/23 failed inspection report and am requesting this meeting occur as soon as possible.

       

      The failed inspection report from 2/17/23 will be uploaded  and emailed to Father and Son's Home Improvement once I have received it. 

       

      Sincerely,

      *************************

    • Complaint Type:
      Order Issues
      Status:
      Answered
      I contacted Father and Sons Remodeling to install a dormer on my home. I signed the contract & also made a $6,000 down payment on 2/10/22. I was promised that the work would start the 1st of spring it is now 10/10/22 and no work has begun. My village requested that the contractor pay a $2,000 deposit towards incidentals and $ 883 for the permit which was included in my price but Father and Sons is demanding that I make the payment to the village. My village also informed me that the contractor has not provided them with licenses. The contractor is telling me that he has given the village $10,000 but the village states they have not received a dime. I should have know better when the contractor negotiated, renegotiated and in tern canceled on replacing the floors in the impacted area. We are now approaching winter, Ive rearranged my home in preparation for work to start and nothings happening. My husband has severe and chronic health issues I cant afford to have my roof torn off in the middle of a ******* winter by a contractor who has already not been upfront, truthful and stood behind their promises. This project has already caused me stress. I want a full refund of my $6,000 or the work started within the next 2 weeks and a guaranteed completion date of 11/20/22.

      Business response

      10/11/2022

      We are sorry to hear that ***************** is stressed; however, she is the one holding the project. 
      We did not promise ***************** a starting date. We can't give our customers a starting date without a building permit. 
      ***************** signed a contract with us on February 10, 2022, to build 2 dormers for closet space and gave us a deposit of $6,000.00. We hired a licensed state architect to prepare architectural drawings. On April 22, 2022, the architect completed the architectural drawings. After several meetings with ***************** and modifications to the drawings ***************** approved the drawings on July 20, 2022. We applied for a building permit on August 9, 2022, and the building permit was approved on September 15, 2022. We are waiting for the customer to pay for the building permit. As we informed *****************, we are not responsible for any permit fees or related fees to obtain the building permit. As a General Contractor, we have a surety bond of $10,000.00 for the *******************. 
      Attached is a copy of the contract and the bond. We will schedule the work as soon as ***************** obtains her building permit. 

       

      Customer response

      10/26/2022

       
      Complaint: 18192741

      I am rejecting this response because:

      Please reopen my case I have been having trouble with my e-mail . Send all replys to this email . ***  (owner) came to my house . He asked me was I going to buy the permit or him I said, you buy it and start the work once you get it . I signed a agreement . Later we added changes he had me sign another document. Our agreement was in February he didnt have all his license until October. I was going to pay for the permit. I bought it and took it to the village. She told me he didnt have his roofing license. And she couldnt take my money. He also told me he gave the village ten thousand dollars. The village said he was lieing. He didnt give one *****. The  village phone number is *************. Please ask the permit department. They will backup what I said. Please have him return all my money because it was his fault. He want me to pay two thousand dollars to cover if they destroy anything . I will not pay if his workers damage anything. That is why he is holding up my job.

      Sent from my iPhone



      Sincerely,

      *************************

      Business response

      11/21/2022

      ****** has a contract with us to build 2 dormers for closet space, and she gave us a deposit of $6,000.00. We hired a licensed Architect to prepare architectural drawings for the project.
       
      The ******************* approved her project on September 15, 2022. We are waiting for her to pay for the building permit. Per our contract, we informed ***************** that we are not responsible for any permit fees or related fees to obtain the building permit. As General contractors, we have a surety bond of $10,000.00 with the *******************. We are not responsible for the refundable bond that the ******************* requests.
       
      We have been waiting for ***************** since September 2022. We can schedule her project as soon as she provides us with a copy of the building permit, or we can cancel her project.
       
      Please let us know how she would like us to proceed or if you need additional information.

      Thank you 

    • Complaint Type:
      Order Issues
      Status:
      Answered
      I have a contract with them in July of 2020, the job was to add an addition onto my house. I have one currently but I do not like it so I was to have the old one taken down and a new one built. They said covid was delaying work. I was talking back and forth with the Supervisor recently. But because of all the back and forth with the Father and Sons, I hired another contractor to hired supervise their work. I called them 3 weeks ago to talk to the manager and a woman in charge but no ones cb. Last Saturday a woman named ***** said to come by, All we need now is a starting date. everything has been approved. They wanted me to come into the office to approve changes, I was never shown these changes or told about them, They are nto allowed to make these changes without the ********* or Supervisor I hired because the original drawings had already been approved by the city of Chicago. I dont know what these changes are. But they have never sent me copies and made changes without my or my contractors knowledge. I want the job completed with the original drawings approved by the city of chicago and me and my contractor.

      Business response

      11/13/2021

      Dear ********************,
      As we informed you, we need to schedule a meeting with you,and the contractor you hired is welcome to attend the meeting.
      We need to meet with you to discuss your project, so there is no misunderstanding; we want to explain how the new addition will tie to your existing dormer.
      We appreciate your patience, but we need your cooperation.We need to have a meeting in our office, and if you wish to cancel the contract, we will refund all the money you paid less the expenses which have occurred to date.
      Please give us a call. 

      Thank you 

      ***************************

      Father and Sons Home Improvement II, Inc.

      28 East Ave

      *******************.

      Customer response

      11/29/2021

       
      Complaint: ********

      I am rejecting this response because:

      Sincerely,

      *****************************

      In regards to case #******** Im rejecting the response from Father and Sons Home Improvement ll. The reason for me rejecting this response is due to the fact that The *************** approved on a drawing I have also agreed upon. But the Father and Son Home Improvement ll company came to me with a different drawing that the city and I did not approve of. If possible I would like to have a hearing between the Father and Sons Home Improvement ll company and myself; in regards to Case #********.

       

    • Complaint Type:
      Billing Issues
      Status:
      Answered
      On March 16th we had father and son come out to give us an estimate on home repairs. They sent the salesman out who gave us a price on the project and what he was going to do. We told him we would have to finance the project he said no problem we finance our self. So we said okay we don't have to go any further looking for a finance company, so he gave us a price of $45,000 and the starting date will begin in May. He acts could we put any money down we agreed to put $3,000 down we were assuming since he said they finance this will go towards the price which he agreed. He told us he was the owner with his son son, so we feel good about the project . We called in May to ask when they were going to start that's when we found out he wasn't the owner and he sent our paperwork to a finance company. The finance company wouldn't finance us so we asked for a refund of our money. He told us we couldn't get a refund because we signed a contract we never received a contract .

      Business response

      07/07/2021

      Mr. ***** signed a contract with us on March 9th, 2021, he was provided with a copy. He also came into our office on April 19th to review the preliminary drawings and Contract. Attached is a copy of the Contract. The Village of Maywood approved the Architectural drawings and Building Permit on May 27th, 2021. Since this day, we have been ready and willing to start Mr. *****'s project. However, he still doesn't have the funds available for his remodeling project. 
      When Mr. ***** signed the Contract, we referred him to Brendan Financial Inc. to obtain a loan for his remodeling project. Brendan Financial Inc. has been working to assist him with a loan for his project. This morning, we contacted Brendan Financial, Inc. to determine why Mr. *****'s loan was denied. Brendan Financial Inc. informed us that the loan was not denied, and they have a pending loan application for Mr. *****. Attached is the email that Brendan Financial Inc. sent us this morning. 

      Mr. ***** does not have to obtain the loan for his project from Brendan Financial Inc. He can obtain the loan from a different lender. 

      We are ready and willing to start his project as soon as he informs us that he has the funds available. No start date was promised to Mr. *****, because we can not start without a building permit. 

      Customer response

      07/09/2021


      Complaint: 15626750

      I am rejecting this response because:

      Sincerely,

      Willie *****
    • Complaint Type:
      Service or Repair Issues
      Status:
      Answered
      This Company's work ethic and communication is terrible. I had 2 items taken from my home from someone they hired. They should be trustworthy and they are not. They are over priced and under deliver. My addition is only 200 Sq feet and is taking over a year to complete. Not to mention the owner is rude and disrespectful. Signing on with father and sons was the worst decision I could make for my home.

      Business response

      05/18/2021

      We understand your frustration. As you know, we couldn't start your project until a permit was issued, which was at the end of October 23, 2020. Since we began your project, we have faced different challenges, with the main one working during a pandemic. We are doing everything possible to complete your project. As of today, we have replaced the windows at your home, remodel your kitchen, pour a rear foundation for a new addition, built a rear addition, installed new siding, shingles, windows, rough plumbing, electricity, and ductwork for your new addition. We should be done with your rear addition soon. We appreciate your patience. 

      Please let us know when this accident occurred. This is something new to us regarding items missing from your home. Thank you

       

    Some consumers may elect to not publish the details of their complaints, some complaints may not meet BBB's standards for publication, or BBB may display a portion of complaints when a high volume is received for a particular business.

    BBB Business Profiles may not be reproduced for sales or promotional purposes.

    BBB Business Profiles are provided solely to assist you in exercising your own best judgment. BBB asks third parties who publish complaints, reviews and/or responses on this website to affirm that the information provided is accurate. However, BBB does not verify the accuracy of information provided by third parties, and does not guarantee the accuracy of any information in Business Profiles.

    When considering complaint information, please take into account the company's size and volume of transactions, and understand that the nature of complaints and a firm's responses to them are often more important than the number of complaints.

    BBB Business Profiles generally cover a three-year reporting period. BBB Business Profiles are subject to change at any time. If you choose to do business with this business, please let the business know that you contacted BBB for a BBB Business Profile.

    As a matter of policy, BBB does not endorse any product, service or business.